Dear owners,

The works carried out during the previous weeks (1 & 2) have focused on the following:

  • Phases 3 & 4 Tree pruning.
  • Phase 4 Blowing of roads and pathways for sweeper lorry.
  • Phases 4 & 5 grass & leaf raking.
  • Olive tree pruning in Phases 1, 2, 4, 6 & Council areas.
  • Hedge trimming and cleaning at El Casón, HR entrance, etc.
  • Gravel raking on Polaris lines in all phases.
  • Manual weeding in Phase 2.

Below is the schedule for this week´s work (week 3).

Week 3 – From 15th to 20th January 2024

Please note that the schedule of the gardening tasks may be interrupted due to weather (rain, wind, etc.)

Estimados propietarios,

Los trabajos realizados durante las semanas anteriores (1 y 2) se han centrado en lo siguiente:

  • Fases 3 y 4 Poda de árboles.
  • Fase 4 Soplado de calles y caminos para camión barredora.
  • Rastrillado de hierba y hojas en las Fases 4 y 5.
  • Poda de olivos en las Fases 1, 2, 4, 6 y zonas del Consejo.
  • Recorte de setos y limpieza en El Casón, entrada HR, etc.
  • Rastrillado de grava en líneas Polaris en todas las fases.
  • Desbroce manual en Fase 2.

A continuación se muestra el programa de trabajo de esta semana (semana 3).

Semana 3 – Del 15 al 20 de enero de 2024

Tenga en cuenta que el horario de las tareas de jardinería puede verse interrumpido debido a las condiciones meteorológicas (lluvia, viento, etc.).

Categories: 2024