The works carried out during the previous week (33) have focused on the following:

  • Phases 1, 4, El Cason & entrance of Resort, manual irrigation.
  • Phase 1, 5A, 5B, 6 & 7 blowing of leaves for sweeper truck.
  • Phases 2, 3, 5B, pruning of trees.
  • Phases 5B & 2, manual weeding.
  • Revision of irrigation system around all 19 swimming pools.
  • Phase 3, grass cutting.
  • Resolving irrigation issues.
  • Raking of gravel in all phases.

Below is the schedule for this week´s work (week 34).

Week 34 – From 19th to 24th August 2024

IMPORTANT INFORMATION

Due to the heat protocol that STV workers are subject to, some activities may be paused or cancelled due to the high temperatures expected this week. Likewise, some activities planned for this week, such as grass cutting, will be carried out as carefully as possible. The dryness of the terrain causes dust to be generated during the activity.

Categories: 2024